Buttimer have been working with Arrabawn Co-op to upgrade and increase the capacity of their existing milk processing facility in Nenagh, Co Tipperary. The scope of Buttimer’s services for Arrabawn Coop has included the specialist installation of a range of plant and vessels on-site for the creation of milk powders and associated products. The installation project began in February 2015 and is scheduled to last for three months.
Buttimer was also contracted, by a leading diary technology equipment supplier, to manufacture a large high-quality stainless steel processing vessel for the Arrabawn Co-op project, which has now been installed: see Buttimer’s Specialist Labour team lifting the unit into place in the below pictures. The specialist piece of equipment was designed by the American dairy technology company, and fabricated under licence at Buttimer Engineering’s workshop in Cahir, Co Tipperary.